11/1/2024 – Industry / Innovation and Technology Development / The power system / Grid development / About Statnett / Projects Successful go-live of the Nordic Flow-based Market Coupling project
Article Statnett applies for temporary measures at Hamang substation On 23 May 2016, Statnett applied to the Norwegian Water Resources and Energy Directorate (NVE) for a licence to implement temporary measures at Hamang substation. The temporary measures will provid …
Article Licence for Hamang substation The Ministry of Petroleum and Energy has granted Statnett a licence to construct a compact station facility (SF 6 facility) at Hamang in Bærum municipality.
Article Temporary restructuring of Hamang substation Statnett SF has rerouted both power lines from Sylling to Hamang substation in Bærum municipality.
Article Bærum municipality appeals NVE decision Bærum municipality has objected to the NVE’s licence decision and wants a licence decision for alternative 2 in the licence application.